Construction associated with the FAA grant for security and safety improvements to the Pearland Regional Airport began today, Monday, May 21.
"We will work closely with the engineer, contractor and inspector to minimize disruptions as best we can," said a representative of the airport.
Below you'll find an overview of the project. The dates listed are subject to change based on weather.
Phase 1: Remove pavement markings east of Runway 14/32
Monday, May 21 - Friday, May 25
Phase 2: Remove pavement markings west of Runway 14/32
Saturday, May 26 - Monday, June 4
Phase 3: Remove pavement markings on Taxiway Alpha
Tuesday, June 5 - Saturday, June 9
Phase 4: Remove pavement markings and re-stripe Runway 14/32 (includes vault work and electrical work in along Runway 14/32)
Sunday, June 10 - Tuesday, June 19
Phase 5: Re-stripe pavement markings on all non-runway surfaces
Wednesday, June 20 - Saturday, June 24
Throughout the entire project, crews will be working on electrical and will be replacing gates and signs outside of the Runway Safety Area (RSA).
They anticipate the entire project will wrap up by Wednesday, July 4.
During construction, should you have any questions or concerns, please call them at (281) 482-7551.
This grant project is administered by TxDOT Aviation, engineered by RSP Klotz, and the contractor is Airfield Western. We will be able to pass along issues to the appropriate person and attempt to answer your questions as expeditiously as possible.